Bodell’s scope of work for the Cherokee Natural Gas Supply Project consists of three parts:
- Xcel’s Ft. Lupton Meter Station #2 which will connect three gas source lines into the new 24″ transmission pipeline
- Instrumentation and communication for seven remotely actuated mainline valves including installation of concrete pads, RTU panels, antenna and TEG
- Xcel’s Cherokee Power Plant Meter Station #3 which will meter the gas to be fed to the combined cycle turbines