Despite the cold and snowy weather, Bodell crews are busy on the expansion of the Brigham Young University-Provo central heating plant and have been setting forms and installing reinforcing steel, as they prepare for the last lift of the concrete walls for the turbine enclosure.
Meanwhile, high-temperature water bypasses on the main header, and valve stations on the make-up water system are readied for tie-ins later this Spring.