The best time to place concrete during the hot summer is early in the morning. We’ve got the first of two lagoons laid down. The concrete lining of the…
The installation of a new 10,000-gallon aboveground diesel fuel tank is now in place along with the systems large backup generator. Piping, supports, oil water separator, with sewer tie…
During the summer of 2018, the Dollar Ridge fire burned approximately 70,000 acres of watershed west of Starvation Reservoir. Following the fire, thunderstorms eroded the burn area causing sediment to…
Bodell crews are replacing and upgrading the aged underground piping that will eventually connect with the new pump house. This includes over 11,900 linear feet of new piping, supports, fittings,…
Notable action occurring on site this month while working with Parker Crane to place and bolt in structural steel columns, girts, and bracing for the pump shelter building. In…
Our first phase is off to a good start with installation of new generator, 10,000 gallon diesel tank, water lines, fuel lines, and finish concrete pads for new equipment… all…
The primary goal of this conference was to align us as a company behind a current mission and long-term vision based upon fundamental business principles and company-specific values – the…
Congratulations Brigham Young University and the Bodell Construction project team for being honored by Utah Construction and Design magazine at their hosted Annual Awards Breakfast December 10, 2019. Here’s a…